If you're working out how to install pallet racking in your unit, delivery day is the first deadline. The lorry leaves quickly and each frame is at least 3m tall. The floor and the lifting gear need to be ready before it arrives.
This guide covers the order the job goes in, with the safety points in the steps where they apply. It's written around our boltless Kimer racking, and it says where you should hand the work to an installer.
Estimated reading time: 8 minutes
In this article:
- How do you install pallet racking?
- What you need to install pallet racking
- Step 1: prepare the floor and the unloading
- Step 2: mark the layout on the floor
- Step 3: stand the starter frames
- Step 4: fit the beams and locking pins
- Step 5: plumb and anchor the starter bay
- Step 6: add the extender bays
- Step 7: fit the load capacity signs
- Does pallet racking need to be bolted to the floor?
- How many people do you need to install racking?
- Do you need to be qualified to install racking?
- How do you keep new racking safe once it's up?
How do you install pallet racking?
To install pallet racking, mark the layout on the floor, stand the starter bay, fit its beams and locking pins then plumb it and anchor it to the slab. Add each extender bay in turn (repeating those steps) and finish with a load capacity sign on every bay. A competent person should carry out the installation, following the manufacturer’s instructions. Our industrial pallet racking range includes the Kimer starter and extender bays used in this guide.
In this guide, a frame is the tall section that stands on the floor on its baseplates (the steel plates at its foot), and its uprights are the vertical posts. Beams are the horizontal bars that span between two frames, and two frames with their beams make a bay. The starter bay is the first one, and each extender bay after it shares a frame with the one before.
What you need to install pallet racking
Putting up pallet racking takes lifting gear, tools for drilling and anchoring, measuring kit and the manufacturer's instructions. Boltless beams need no screws or special tools. Most of the kit you need to assemble pallet racking is for lifting and floor fixing. Have these ready before the frames arrive:
- The manufacturer's instructions, which give every figure that belongs to the maker (anchor size and allowed lean, for example)
- Your layout plan, ours or your installer's, kept on site
- A scissor lift to stand the frames
- A lifting platform (scissor lift) that reaches the top beam level, to fit the upper beams
- A hammer drill with a masonry bit of the size the anchor specifies
- A socket set or torque wrench for tightening the anchors
- Anchor bolts to the maker's specification
- A rubber mallet for seating the beams
- A tape measure and chalk line, plus a spirit level or plumb line
- Safety boots, gloves, a hard hat, eye protection and a dust mask for the drilling
Settle the lifting gear first, since it decides whether the frames can be stood at all.
Step 1: prepare the floor and the unloading
Before the lorry arrives, check that the slab is sound and have the lifting gear waiting on site. Walk the area where the racking will stand, looking for cracks or any other part of the slab that isn't sound. A crumbling edge or a repaired strip under a frame is a reason to stop and get it looked at before you drill.
If the floor slopes enough to stop a frame sitting plumb (straight up, with no lean), stop there too. Ask us or the manufacturer before you pack anything underneath.
The driver normally can't stay long. Access and timing are on our delivery information page.
Count what arrives against the delivery note and set aside any frame with a visible bend. Lay the frames out close to where they'll go and clear of the first bay, so you don't handle them twice.
Step 2: mark the layout on the floor
Marking the layout starts with a chalk line for the starter bay, and you measure everything else from it. The walls of a unit aren't always square to each other. When you set up a run off a wall, it inherits whatever error that wall has.
Mark the position of each baseplate then measure both diagonals of the starter bay footprint. When they match, the footprint is square.
The distance from the wall and the aisle widths come from your layout and the truck's datasheet, because clearances depend on the truck.
Chalk the full run before the first frame goes up. A column or a doorway that cuts into an aisle the truck has to turn in then shows on the floor before anything is built.
Step 3: stand the starter frames
The starter bay's two frames go up first. Lift each onto its marks with lifting gear suited to a frame this tall, with at least two people on the ground beside it. The Kimer starter bay comes with two full end frames and is the base every extender builds on.
Both baseplates should sit flat on their chalk marks, with the frame square to the line. A frame standing on its baseplates alone can go over with very little push. Hold each one with the lifting gear or a second person until its beams and pins are in.
If you're unsure how the two frames sit in relation to each other, check the manufacturer's instructions before fitting the first beam.
Step 4: fit the beams and locking pins
Fit the beams from the lowest level upwards, working from a lifting platform, since the low beams tie the two frames together first. Set each level at the height your layout gives, or the manufacturer's instructions if your layout doesn't say. Tap each beam end into its connectors with a rubber mallet until it's fully seated.
Check as you go that both ends of a beam sit at the same height and that each beam is level against its neighbour. Each gap between levels has to hold a loaded pallet plus the lift clearance the maker specifies. A gap that's too tight only shows itself the first time a forklift tries to place a pallet.
Fit a locking pin in every beam end connector, one per end. The locking safety pins for Kimer pallet racking come with new beams, and we sell packs of 50 if any go missing. A beam that seems solid without its pin can lift out when a fork or a pallet catches it from underneath.
Until the anchors are in, don't load the beams. Don't lean on an unanchored frame or climb it either.
Step 5: plumb and anchor the starter bay
Check that the starter bay is plumb in both directions, then anchor it, before you add anything to it. Hold a spirit level or plumb line against each upright, once looking along the aisle and once across it. The manufacturer's instructions give the allowed lean, and a starter bay that leans carries its error into every bay built from it.
If the frame won't come true, stop and call us.
When the bay is true, anchor each frame to the floor. Drill through the baseplate holes, clear the dust from each hole, set the anchor and tighten it to the manufacturer's setting. The anchor type and the hole size and depth come from the same instructions. We sell pallet racking anchor bolts in packs of 50.
Over-tightening can damage the anchor or drag the frame out of plumb. Stop at the maker's setting, then check the level again once the last anchor is down. You're finished when every upright reads true in both directions and none has shifted since the first anchor went in.
Step 6: add the extender bays
Add each extender bay one at a time, repeating the frame, beams, pins, plumb and anchor sequence on every one. The Kimer extender bay connects onto the starter and shares one of its frames. Each new bay needs a single new frame and its beams.
You'll know the run is true when the beams of neighbouring bays line up across the shared frame and every pin is in. Run the tape along the chalk lines again every couple of bays. A small drift in the first bays tends to show up as a visible one by the tenth.
Step 7: fit the load capacity signs
Every bay needs its own load capacity sign. Fix it where a driver can read it from the aisle, once the beams are in their final positions.
Fill in the figures for that bay from the manufacturer's instructions or your layout. The same frame carries a different load depending on where its beams sit. A figure copied from the next bay along is likely to be wrong.
Does pallet racking need to be bolted to the floor?
Pallet racking does need to be anchored to the floor, even though the beams are boltless. The Health and Safety Authority (HSA) says in its work at height and falling objects information sheet that racking must be erected as per the manufacturer's instructions, including appropriate security and anchorage.
How many people do you need to install racking?
You need at least two people for every frame, because the shortest frame we sell is 3m. A lifting platform adds its operator to the crew. Plan the crew by counting frames, not bays, since the hours usually go on drilling and anchoring.
Do you need to be qualified to install racking?
The Health and Safety Authority doesn't name a qualification for installing racking in its information sheet. Whoever drives the platform or the truck still needs training to use it. Keep the area under a standing frame clear of everyone else. Beyond that the judgement is yours, and we'd hand the job to an installer in any of these situations:
- The slab is cracked or patched under a baseplate, or you aren't sure what it's made of
- The top beams sit higher than your lifting kit can reach with someone working safely at that height
- You can't spare two people with experience of working at height
- The manufacturer's instructions are missing or don't match your layout
We quote installation from the pallets you store and the forklifts you use - have both to hand when you get in touch.
How do you keep new racking safe once it's up?
You keep new racking safe by protecting the uprights and checking the racking regularly for damage. The HSA sheet says uprights must be protected from impact, and that damaged racking must not be used until it's repaired or replaced.
Forklifts are usually what hit uprights. The HDPE upright protectors in our racking accessories range come in 80mm and 120mm sizes. Pick the one that matches your upright width and ask us if you're unsure. We list the 80mm for 80mm profiles and the 120mm for 100mm to 120mm. We recommend buying fitting arms for both, to fix them to the upright.
A frame protector guard takes the knock at the end of a run in place of the frame. Use a single guard at the end of a run along a wall and a double guard at the open end of a back-to-back pair.
If you're unsure about any of this, take a look at our pallet racking installation service or get in touch on +353 (0)90 9673261 and we'll talk it through.
Disclaimer: This guide gives general information on installing pallet racking. It doesn’t replace the manufacturer’s instructions or a qualified installer’s advice on your site. Floors, equipment and layouts differ, so we can’t accept responsibility for installations carried out from this guide alone. If you’re unsure about any step, call us on +353 (0)90 9673261 or ask about our pallet racking installation service.